Fire Escape Improvements  

Work included: 

Undertake a GPR Survey & record the results of the survey. 
Excavation of existing path materials, including granular dust and sub-base. 
Installation of PCC edgings. 
Replacement of defective manhole covers & adjustment of other covers & frames. 
Laying of imported Type 3 sub-base to enable drainage percolation. 
Handlay AC10 open graded permeable bitumen macadam. 
Install 18mm depth of Sureset permeable resin bound material in 6mm Mahogany. 
Compaction using a Power float for an improved finish. 
Investigate, design and install new building mounted LED lighting with PIR activation to illuminate new footpath. 

Info: 

Duration: 
3 Weeks 
Client: 
VIVO Defence Services 
Value: 
£41,000.00 

Innovation: 

A key innovation within the project was the introduction of a fully permeable footpath construction designed to improve surface water management and reduce standing water issues. The permeable pavement build-up, incorporating Type 3 sub-base, open graded asphalt, and resin bound surfacing, enabled natural drainage infiltration while delivering a high-quality pedestrian finish. 