Tuffley Park Footpath 

Work included: 

Excavate 2.0m wide footpath to formation level. 
Install timber edging with timber pegs. 
Lay a Geo-textile membrane. 
Lay & compact 100mm thick of MOT Type 1 sub-base material. 
Lay & compact 50mm depth of Breedon Gravel (12mm to fines). 
Reinstate grass verge areas & re-seed. 
Removal of all spoils off site to license waste facility. 

Info: 

Duration: 
3 Weeks 
Client: 
Gloucester City Council 
Value: 
£27,000.00 

Innovation: 

As Benchmark were able to work within the confines of the budget, the client issued a variation to construct an additional entrance hardstanding area, in the same specification as the footpath. 